Work item: HS2-EW-BBVS-Ph1-OOC-St-S4-UT-8-29/04/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Old Oak
- Contractor
- BBVS JV
- Type of works
- Ground investigations, Utility works / surveys
- Estimated Start Date
- 04/05/2021
- Estimated End Date
- 04/06/2021
What we are doing
Work is continuing to create the new access routes to the two worksites on Wormwood Scrubs via Old Oak Common Lane. The next phase of these works will begin from 4 May 2021, and involve further ground and utilities investigation works, as well as clearance of the stumps remaining following earlier vegetation removal works. These works will continue to be accessed via the existing maintenance access route off Braybrook Street as agreed with Hammersmith & Fulham, until the new access from Old Oak Common Lane has been constructed and track matting will be in place to protect the ground along this route.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]