Update Notice: Work on Wormwood Scrubs

Work item: HS2-EW-BBVS-Ph1-OOC-St-S4-UT-8-29/04/2021

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Location
Old Oak
Contractor
BBVS JV
Type of works
Ground investigations, Utility works / surveys
Estimated Start Date
04/05/2021
Estimated End Date
04/06/2021

What we are doing

Work is continuing to create the new access routes to the two worksites on Wormwood Scrubs via Old Oak Common Lane. The next phase of these works will begin from 4 May 2021, and involve further ground and utilities investigation works, as well as clearance of the stumps remaining following earlier vegetation removal works. These works will continue to be accessed via the existing maintenance access route off Braybrook Street as agreed with Hammersmith & Fulham, until the new access from Old Oak Common Lane has been constructed and track matting will be in place to protect the ground along this route.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]