Update of utility works in your local area – Showing location for Alperton Lane
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-20/05/22
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Greenford
- Worksite Name
- Westgate
- Contractor
- SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 06/06/2022
- Estimated End Date
- 24/06/2022
What we are doing
Ground investigation works on Alperton Lane
From 13 to 24 June 2022, we will be carrying additional ground investigation works on Alperton Lane between 8am to 6pm Monday to Friday and 8am to 1pm, Saturdays. The utility surveys will take place on the footpath on Alperton Lane, near the junction with Manor Farm Road.
The ground investigations will consist of digging a temporary trench to confirm the location of utilities under the surface of the footpath. The surveys will help us to understand and aid the design of the new railway and the best ways to protect or divert any utilities during construction.
You may hear additional noise during these works. We will use noise reducing barriers, where possible.
You can view a map showing the location of these works below.
Ground investigation works on May Gardens
We recently had a temporary road closure in place at the junction of May Gardens and Alperton Lane to carry to out ground investigation works.
From 6 to 17 June 2022, we will be carrying additional ground investigation works on May Gardens between 8am to 6pm Monday to Friday and 8am to 1pm, Saturdays. The ground investigations will consist of digging a temporary trench to confirm the location of utilities under the surface of the road.
A temporary road closure will be in place at the junction of May Gardens and Lily Gardens. A signed diversion route will be in place for local road users via Alperton Lane, Manor Farm Road, Pleasant Way, Lily Gardens and May Gardens.
You can view the location of these works on the map below:
The dates of the works may change, we will provide updates at HS2.org.uk/in-your-area/map