Update of works at Atlas Road roundabout in Victoria Road

Work item: HS2-EW-CSJV-Ph1-OOC-St-S4-UT-11-16/04/2021

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Location
Old Oak, Victoria Road
Contractor
CS JV
Type of works
Utility works / surveys
Estimated Start Date
19/04/2021
Estimated End Date
31/03/2022

What we are doing

Tunnel Boring Machine power supply works

We previously notified you of the utility works for the Tunnel Boring Machine power supply.

What are we doing?

We are continuing with the programme of utility works in the Old Oak area, to provide power for the Tunnel Boring Machine to aid with the construction of the HS2 tunnels at the Victoria Crossover box (VCB) in Victoria Road.

Atlas Road – phase 1 of the works continue in Atlas Road includes the laying of electrical power connections that will supply the power for the Tunnel Boring Machine and are scheduled to complete by 7th May.

Victoria Road – from the beginning of May a series of utility works will be carried out in multiple phases in Victoria Road until March 2022. One lane of traffic will always be open to traffic during the works with each phase detailed overleaf and a map showing their locations.

Please be aware that the dates of works are indicative and may change as the works progress. Please sign up to receive updates at www.HS2inOldOak.co.uk

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]