Update of works at Canterbury Works site
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-2-23/07/21
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Canterbury Road
- Worksite Name
- Canterbury Works
- Contractor
- SCS JV
- Type of works
- Piling
- Estimated Start Date
- 02/08/2021
- Estimated End Date
- 09/08/2021
What we are doing
Ongoing piling schedule
We notified you in June 2021 about our piling works at the Canterbury Works site starting on 21 June which we expected to last three weeks. The start date of these works was delayed meaning that the end date has also changed.
We have completed the sheet piling phase along our site border with St Mary’s Catholic Primary School, with the final phase of the piling works along the site boundary with the Network Rail tracks taking place from 2 to 9 August 2021.
We will be working between 8am and 6pm Monday to Friday and 9am and 1pm on Saturdays if required. The location of these works can be found on page 2.
Our piling method
We used a press piling unit to push in the piles along the boundary with the school during the first phase of piling. To protect the nearby Network Rail tracks and trains, our piling method will change for the final phase of piling works between 2 and 9 August to a vibration hammer rig.
During these piling works you may experience some additional noise and vibration. We will be carrying out vibration and noise monitoring to ensure that any disruption is kept to a minimum.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]