Update of works at Canterbury Works site

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-2-23/07/21

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Canterbury Road
Worksite Name
Canterbury Works
Contractor
SCS JV
Type of works
Piling
Estimated Start Date
02/08/2021
Estimated End Date
09/08/2021

What we are doing

Ongoing piling schedule

We notified you in June 2021 about our piling works at the Canterbury Works site starting on 21 June which we expected to last three weeks. The start date of these works was delayed meaning that the end date has also changed.

We have completed the sheet piling phase along our site border with St Mary’s Catholic Primary School, with the final phase of the piling works along the site boundary with the Network Rail tracks taking place from 2 to 9 August 2021.
We will be working between 8am and 6pm Monday to Friday and 9am and 1pm on Saturdays if required. The location of these works can be found on page 2.

Our piling method
We used a press piling unit to push in the piles along the boundary with the school during the first phase of piling. To protect the nearby Network Rail tracks and trains, our piling method will change for the final phase of piling works between 2 and 9 August to a vibration hammer rig.

During these piling works you may experience some additional noise and vibration. We will be carrying out vibration and noise monitoring to ensure that any disruption is kept to a minimum.