Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-34-22/01/2022_05
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Mandeville Road
- Worksite Name
- Mandeville Road
- Contractor
- SCS JV
- Type of works
- Road repairs
- Estimated Start Date
- 02/12/2022
- Estimated End Date
- 04/12/2022
What we are doing
What we are doing
We wrote to you in July to update you on the preparation of the access ramp in front of the site office and down to the lower works area.
We need another few days to complete this work and we plan to do this over the weekend of 2 to 4 December.
On 2 December 2022, we will continue to prepare the access road in front of the site office. Some excavating and compacting of the area will be required.
On 3 and 4 December 2022, we will be installing a layer of tarmac on the access road at the front of the site office as well as the lower platform down at railway level.
You may smell the tarmac being laid during this time.
We would like to apologise in advance for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way. We will ensure that disruption is kept to a minimum.