Update on concrete breakout works, Mandeville Road Vent Shaft site

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-Works-2-25/07/2024_01

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Mandeville Road
Worksite Name
Mandeville Road
Contractor
SCS JV
Type of works
Concrete break out
Estimated Start Date
23/09/2024
Estimated End Date
08/11/2024

What we are doing

What we are doing – Break out of concrete
We wrote to you on the 26 July 2024, to let you know that we would start to remove a one-metre-deep concrete slab from the bottom of the satellite shaft on 5 August 2024. The start of these works was dependent on the progress of the tunnel boring machines.

Due to required maintenance on the tunnel boring machines, the dates for these works have now changed and will now start on 23 September 2024.

These works will be carried out using high-pressure water jet machinery, petrol saws and excavators. We will use noise reducing barriers to help keep noise to a minimum. We will work as efficiently as possible, while keeping our work areas safe and tidy.