Update on concrete pours at Mandeville Road Site
Work item: HS2-MW-SCS-Ph1-Ar-So-S2-Prog-works-01-22/01/2024_02
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Mandeville Road
- Worksite Name
- Mandeville Road
- Contractor
- SCS JV
- Type of works
- Concrete pours
- Estimated Start Date
- 17/02/2024
- Estimated End Date
- 17/02/2024
What we are doing
What we are doing
On 17 February 2024, deliveries to Mandeville Road Ventilation Shaft site will occur more regularly to enable continuous concrete pours into the Satellite Shaft. We expect this to be between 6am and 1pm. The concrete pours must be uninterrupted, in order to maintain the structural integrity of the shaft walls.
There will be a delivery of machinery at 6am on 17 February 2024, ready for an 8am start. The machinery will be removed once the concrete pour is complete, which we estimate to be between 2pm and 3pm. We will close Mandeville Road, so that we can reverse a lorry out of the site to remove the machinery.
While on-site work is not expected to cause additional disruption, more delivery vehicles will be present due to the quantity of concrete that is required. Traffic Marshals will guide delivery vehicles as usual. Noise and vibration monitoring will continue, with extra noise suppression if needed.
We would like to apologise for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way.