Skip to main page content
View route map

Update on earthworks at the site on Breakspear Road South

Work item: S2-EW-SCS-Ph1-Ar-So-S2-Prog-works-1-05/05/2025_03

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Worksite Name
Breakspear Road South
Contractor
SCS JV
Estimated Start Date
17/06/2024
Estimated End Date
05/05/2025

What we are doing

We wrote to you in December 2024 to update you on works for the retained embankments construction at our site on Breakspear Road South, from 17 June 2024 to 31 March 2025.

We are building the embankments using lorries to deliver aggregate, machinery to place the material and compaction equipment, including vibratory rollers.

These works have been delayed due to reduced availability of lorry deliveries. Our permitted lorry movements are limited, and we had to use some of them to move tunnelling materials off-site during this period of works.

In addition, heavy rain in January and February made it impossible to carry out the required compaction tests for the embankments. As a result, we now expect to complete the works by 5 May 2025.

We need 11,000 tonnes of material to complete the embankments, using lorries for delivery of aggregate, machinery to place the material, and compaction plants, including vibratory rollers.

These works create some noise due to the use of ground compaction equipment and excavator activities. Every effort is being taken to ensure that these works are carried out in the least impactful way, and we will ensure that disruption is kept to a minimum.

For further details please see update notification below.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]