Update on Interim Taxi rank works on Eversholt Street and Upper Woburn Place

Work item: HS2-MW-MD-Ph1-Eu-St-S3-CR-45-11/09/2023

Work Item Summary

Project Phase
Phase 1
Location
Camden
Worksite Name
Euston Station
Contractor
Mace Dragados JV
Type of works
Construction, Monitoring equipment
Estimated Start Date
18/09/2023
Estimated End Date
30/11/2023

What we are doing

From 18th September London Borough Camden will install CCTV cameras on Eversholt Street of on behalf of Mace Dragados. To facilitate the works, one parking bay will be suspended on Wesley Place. The works are expected to take place for approximately 3 weeks at night.

From early October until late November, Mace Dragados we will install Variable-Message Signs (VMS) on Eversholt Street and Upper Woburn Place. The VMS will alert taxis if the new facility is full. The construction of these activities will consist of breaking out sections of the pavements to install the CCTV cameras, install ducting for the VMS and reinstate the pavements. There will be barriers around the worksites and local traffic management. Pedestrian crossings and roads will remain in use throughout these works. Please see further details below.

Previous notification regarding Interim Taxi Rank works, here (June 2023) (Reference number: HS2-MW-MD-Ph1-Eu-St-S3-Prog-Works14-02/06/2023

Download information relating to these works