Skip to main page content
View route map

Update on Old Dairy Lane drainage surveys

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog works-1-25/4/22_02

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Location
Old Dairy Lane
Worksite Name
South Ruislip
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
20/09/2022
Estimated End Date
22/09/2022

What we are doing

What we are doing
We wrote to you in April to let you know that we would be carrying out overnight utility surveys on Old Dairy Lane.

We have completed these surveys, however we need to undertake further surveys overnight from 20 to 22 September 2022. We will use CCTV cameras and scanning equipment to carry out the surveys in the area shown on the map overleaf.

How these surveys might affect you
Temporary traffic management and safety zones will be in place to ensure the surveys can be carried out safely. We would like to apologise in advance for the disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way.

We will ensure that disruption is kept to a minimum.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]