Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Old Oak Common
- Worksite Name
- Old Oak Common
- Contractor
- SCS JV
- Type of works
- Works Update
- Estimated Start Date
- 22/04/2024
- Estimated End Date
- 30/09/2024
What we are doing
Construction of this tunnel will start from 22 April 2024 till late summer 2025 and will be 24 hours a day, 7 days a week when required.
Our sprayed concrete lining (SCL) tunnel will connect the Victoria Road Crossover Box (VRCB) to the to the Old Oak Common (OOC) site on Old Oak Common Lane.
The impact of this work on residents on will vary throughout the construction. The first set of impactful works is likely to take place between August – September 2024. Residents will be contacted closer to time about this.