Update: Old Oak Common Tunnel

Work item: HS2-SCS-25-1141

Work Item Summary

Project Phase
Phase 1
Region
London, Old Oak and North Acton
Location
Old Oak Common
Contractor
SCS JV
Type of works
Construction
Estimated Start Date
01/08/2024
Estimated End Date
30/11/2026

What we are doing

We last wrote to you in July 2025 to update you on works to build the Old Oak Common Tunnel.

We have now completed tunnelling phases 1A, 1B and 2 of these works. We are currently continuing phase 2A waterproofing and concrete lining works within the tunnel. We will return to start phase 3 in June 2026.