Update on overnight closures on the A446 Lichfield Road

Work item: HS2-BBV-26-1771

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
A446
Contractor
BBV JV
Type of works
Overnight road closure
Estimated Start Date
08/03/2026
Estimated End Date
13/03/2026

What we are doing

Location
A446 Lichfield Road, near Coleshill

Duration
We previously shared details about the 7-day and overnight road closures on the A446 Lichfield Road. Please see the update below regarding the use of the contingency overnight closures.

Overnight Closures:
The road will be closed overnight between 21:00 and 06:00 on the dates listed below:
Sunday 8 March 2026
Friday 13 March 2026

What we are doing
Transfer of equipment from the A446 Lichfield Road to our compound, following completion of the Water Orton Viaducts spanning the A446 Lichfield Road.

What to expect
• Remaining works will be completed overnight
• Access for pedestrians and cyclists will remain in place throughout the road closure.
• Access to businesses and residents will remain throughout the road closure.
• Bus routes will be diverted accordingly; check bus company website for more information.
• Updates on any changes will be communicated in advance.

HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]