Update on removal of Pipework between South Ruislip and Yeading Brook

Work item: HS2-MW-SCS-Ph1-Ar-So-S1-Traf-33-09/04/2024_02

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Location
South Ruislip
Worksite Name
South Ruislip
Contractor
SCS JV
Type of works
Pipework removal
Estimated Start Date
23/05/2024
Estimated End Date
26/07/2024

What we are doing

We wrote to you on 8 May 2024, to let you know that from 13 May 2024 we would be removing the pipework along the railway embankment from our site in South Ruislip to Yeading Brook. Due to delays in finalising permissions for the works, they will now start from 23 May 2024.

From 23 May to 26 July, we will be removing the pipework as below:

Section one: 23 May to 13 June – South Ruislip Vent Shaft (SRVS) to the bridge on Bridgwater Road.

Section two: 14 June to 26 July – Bridgwater Road to Yeading Brook. Access for materials and plant for this phase will be through the Bridgwater Road fields.

What to expect

During these works, we will be using an excavator, a dumper and small hand tools. We’ll use a transit van to transport people to the works location.

We would like to apologise for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way.