Update on sheet piling at Mandeville Road site
Work item: HS2-MW-SCS-Ph1-Ar-So-S2-Prog-works-1-22/11/2021_02
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Mandeville Road
- Worksite Name
- Mandeville Road
- Contractor
- SCS JV
- Type of works
- Hoarding works, Piling
- Estimated Start Date
- 06/12/2021
- Estimated End Date
- 28/01/2022
What we are doing
Sheet piling
We wrote to you in October to inform you of the upcoming sheet piling and hoarding removal at the northern end of our site. This date has now been rescheduled to start in December.
Due to the supporting concrete blocks being in close proximity to these works, we will need to remove a small section of the existing hoarding, adjacent to the Carr Road access track.
We will replace that section of hoarding with heras fencing with a noise reducing cover to help manage the noise from site. This hoarding will be removed from 6 to 9 December to allow us to survey the ground for high voltage cabling in advance of sheet piling. The hoarding will be reinstated by 28 January 2022.
From 4 to 28 January 2022, we will be installing sheet piling close to the boundary of the northern end of our site, as shown on the map below.
How these works might affect you
You may notice periods of increased noise during these works due to the reduced height in the fencing along the site boundary.
We would like to apologise in advance for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way. We will ensure that disruption is kept to a minimum.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]