Update on sheet piling works at Mandeville Road
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-13-20/07/2021_04
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Mandeville Road
- Worksite Name
- Mandeville Road
- Contractor
- SCS JV
- Type of works
- Piling
- Estimated Start Date
- 21/02/2022
- Estimated End Date
- 31/03/2022
What we are doing
Sheet piling
We wrote to you in December to update you on the installation of sheet piles at our Mandeville Road site.
From 21 February to 31 March 2022, we will continue to install sheet piles at the northern end of our site in the areas shown on the map overleaf.
Due to the proximity of the sheet piling to the hoarding line, a section of the hoarding had to be removed to facilitate these works. The sheet piling has commenced in this area and will progress past the gap in the hoarding by 19 February.
We are creating new footings to cast a reinforced concrete slab that will replace the original concrete blocks that kept the hoarding in place. Once the piling equipment is clear of this area, we will reinstall the hoarding.
This is due to start in mid-March with an anticipated completion date of 31 March 2022.
Download information relating to these works