Update on traffic management on A4097 Kingsbury Road

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-20-14/03/2022

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire, West Midlands
Location
Kingsbury
Worksite Name
A4097 Kingsbury Road
Contractor
BBV JV
Type of works
Road closure, Traffic management
Estimated Start Date
30/10/2022
Estimated End Date
31/05/2023

What we are doing

We are constructing a new roundabout, on the A4097 Kingsbury Road, to provide a safe access and egress to the Kingsbury Main Compound. While constructing the new roundabout, we have had to complete additional works to protect a fuel pipe at this location. During these works we also identified ecological species on site that required further surveys and a hibernation period. These additional works have been completed and have resulted in extending the programme completion date for the new roundabout, to Spring 2023.
To enable us to complete the new roundabout safely, we will switch our traffic management across to the other lane and direct road users around our working area. To install the new traffic management we will require some overnight closures of the A4097 Kingsbury Road.
Some low level noise will be generated from the work we are completing.

When the temporary traffic management will be in place?
Overnight Closures – To enable us to switch the traffic management across we will have overnight closures of the A4097 Kingsbury Road from 30 October to 19 November 2022 between 9pm – 5am. We will also complete utility surveys during the overnight closures.
Single Lane Closure until Spring 2023 – Once the traffic management has been switched over we will have a single lane closure, with temporary traffic lights, in place until Spring 2023.

Download information relating to these works