Update on Transport for London bridge protection works near Herlwyn Avenue
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Tun-1-16/2/23_03
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon, London
- Location
- Ruislip
- Contractor
- SCS JV
- Type of works
- Bridge protection works
- Estimated Start Date
- 22/02/2023
- Estimated End Date
- 15/03/2023
What we are doing
We carried out protection works to the pedestrian footbridge at the Transport for London depot located trackside at the rear of Herlwyn Avenue. Because of proximity to the tracks, works took place overnight on 8 and 15 January when the railway was not operational. To complete the works, we will still need to install stairs to the bridge. These works are due to take place between 22 February and 15 March.