Update on Utilities works on Station Approach and Long Drive, April 2023
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-23/09/2022_03
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon, London
- Location
- South Ruislip
- Contractor
- SCS JV
- Estimated Start Date
- 15/04/2023
- Estimated End Date
- 14/05/2023
What we are doing
Our main sewer protection works on Station Approach and Long Drive have been completed, and we are now due to divert the
watermain from 15 April to 14 May 2023. These works are to redirect the water main and will happen seven days a week from 8am to 6pm, to minimise disruption on the road.
Phase 1: Footpath closure will be in place between the entrance to Long Drive Car Park and the corner of Sainsbury’s from 15 April to 22 April 2023. Pedestrian access will remain open into Sainsbury’s from Long Drive.
Phase 2: Single lane traffic management will be in place on Station Approach from 22 April to 14 May 2023.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]