Update on utility works at High Road and Ickenham Road
Work item: HS2-MW-SCS-Ph1-Ar-So-S2-Prog-Works-35-22/11/2021_05
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Ickenham
- Worksite Name
- West Ruislip
- Contractor
- SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 30/06/2022
- Estimated End Date
- 12/08/2022
What we are doing
What we are doing
We wrote to you recently to let you know that that we would be starting the final phase of the main utility relocation works, near West Ruislip train station. We wanted to complete these works by 30 June, however we will require additional time to complete some repairs on the kerb near the entrance to West Ruislip Portal site from 30 June to 3 July 2022.
The traffic management will be changed on Sunday 3 July to allow us to reinstate the central reservation and pedestrian crossing. During this phase the footpath will be reopened on both sides of the bridge along High Road and Ickenham Road.
We will then start the final phase from 4 July to 12 August 2022.
How these works might affect you
In order to carry out these utility works safely:
– a footpath diversion will be in place including a temporary pedestrian crossing either side of the work area
– the cycle path will be closed for the duration of these works
– the West Ruislip bus Stop M will be suspended and temporarily moved to a safe location.
– the West Ruislip bus Stop S will remain open at all times.
Your utility services will not be affected.
We would like to apologise in advance for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]