Work item: HS2-EW-Align-Ph1-Ar-Ce-C1-CR-27-26/02/2021

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Chalfont St Giles
Contractor
Align JV
Type of works
Construction
Estimated Start Date
01/03/2021
Estimated End Date
31/07/2021

What we are doing

Works to prepare for and the start of diaphragm walling (D-walling) at the vent shaft site at Chalfont St Giles will start in March. The vent shaft is an important structure for the railway because it will provide ventilation for the Chiltern Tunnel under Chalfont St Giles. In March we will take the first steps in its construction.