Update on works at Mandeville Road site
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-34-22/01/2022_02
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Mandeville Road
- Worksite Name
- Mandeville Road
- Contractor
- SCS JV
- Type of works
- Excavation works, Road repairs
- Estimated Start Date
- 20/06/2022
- Estimated End Date
- 26/08/2022
What we are doing
What we are doing
We wrote to you in June to update you on the ongoing works to prepare the site for the construction of the ventilation shaft and headhouse. We have now completed sheet piling and the initial high level bored piling and will continue with excavation on the embankment and resurfacing of the access road.
From 11 to 22 July 2022, we will be preparing the access road in front of the site office and installing tarmac. Some excavating and compacting of the area will be required prior to installing a layer of tarmac. You may smell the tarmac being laid during this time.
We would like to apologise in advance for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way. We will ensure that disruption is kept to a minimum.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]