Update on works at Mandeville Road site
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-34-22/01/2022_04
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Mandeville Road
- Worksite Name
- Mandeville Road
- Contractor
- SCS JV
- Type of works
- Excavation works, Road repairs
- Estimated Start Date
- 25/07/2022
- Estimated End Date
- 05/07/2022
What we are doing
What we are doing
We wrote to you earlier this month to update you on the preparation of the access road in front of the site office. The link to the original notification can be found here: Community notice July 2022
We need to continue with these works following test taken on the ground in this area.
From 25 July to 5 August 2022, we will continue to prepare the access road in front of the site office. Some excavating and compacting of the area will be required.
On Saturday 13 August 2022, we will be installing a layer of tarmac on the access road at the front of the site office as well as the lower platform down at railway level.
You may smell the tarmac being laid during this time.
We would like to apologise in advance for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way.
We will ensure that disruption is kept to a minimum.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]