Update on works at the former Maria Fidelis school site
Work item: HS2-MW-MD-Ph1-Eu-St-S3-Prog-works-12-28/07/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- North Gower Street
- Worksite Name
- Maria Fidelis school site
- Contractor
- Mace Dragados JV
- Type of works
- Cement pours, Construction, Delivery of materials
- Estimated Start Date
- 01/08/2022
- Estimated End Date
- 31/10/2022
What we are doing
Once concrete pouring is complete, we will install a steel frame in August as part of the new superstructure for the Maria Fidelis accommodation block. The frame will be delivered via Cardington Street onto site using articulated wagons. A crane will then lift the frame into position. Once in place, it will be bolted down to the concrete using torque wrenches. Following this, works will commence on placing the cabins into position from late August to October 2022. The cabins will be delivered onto site via Cardington Street on extendable low loaders. A mobile crane will then be used to lift the building cabins into position above the foundation and ground floor steel frame. Once in place, the frame will be bolted down using torque wrenches.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]