Update on works at the former National Temperance Hospital

Work item: HS2-MW-MD-Ph1-Eu-St-S3-Prog-works-12-28/07/2022

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Hampstead Road
Worksite Name
National Temperance Hospital site
Contractor
Mace Dragados JV
Type of works
Hoarding works, Piling
Estimated Start Date
01/08/2022
Estimated End Date
31/07/2023

What we are doing

Enabling works at the former National Temperance Hospital-North is anticipated to be completed by September 2022. Test piling at the former National Temperance Hospital-South is anticipated to be carried out from August to October 2022.

We have been progressing the enabling works and have completed local utility diversions, footpath widening, pile extractions, pile cap removal, petrol tank removal and basement retaining wall removals. The remaining works include the removal of temporary sheet piles before a piling mat will be installed across the site using compacted aggregates. Once the piling mat has been installed, piling works are planned to commence to continue installing the west station wall. These piling works are planned to commence from September to January 2023. We will also be returning the hoarding alignment to its previous position and removing the footpath widening installed within the bus lane.

 

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]