Update on works in Swinfen and Packington

Work item: HS2-MW-BBV-Ph1-Ar-No-N2-Traf-7-27/07/2022

Work Item Summary

Project Phase
Phase 1
Region
Staffordshire, West Midlands
Location
Swinfen
Worksite Name
Packington Moor Farm
Contractor
BBV JV
Type of works
Earth works
Estimated Start Date
11/08/2022
Estimated End Date
31/12/2022

What we are doing

We will be commencing initial earthworks in Swinfen and Packington, including stripping topsoil and reducing the ground level in sections of Swinfen Cutting. We will complete these works within our working area boundary, using large excavators, scrapers, bulldozers and trucks to transport materials to our storage area.
These works will be undertaken between August and December 2022. Our working hours will be 8am to 6pm. Our workforce can be on-site one hour before and after to set up and secure our equipment.

Please see the attached work notice for the area we will be working in.

Download information relating to these works