Update: Ongoing works at the Victoria Road Crossover Box and Flat Iron sites

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-24/04/2023

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Victoria Road, Willesden Euroterminal
Worksite Name
Flat Iron site, Victoria Road, Willesden Euroterminal site
Contractor
SCS JV
Type of works
Construction, TBM Associated Works
Estimated Start Date
01/09/2023
Estimated End Date
08/01/2024

What we are doing

Works are continuing in the Victoria Road Crossover Box site to build the ventilation shaft and crossover box. These structures will regulate air flow, provide access to the tunnels, and allow trains to switch tracks as they enter and leave the future Old Oak Common Lane station.