Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog works-1-30/05/2022

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Canterbury Road
Worksite Name
Canterbury Works
Contractor
SCS JV
Estimated Start Date
08/06/2022
Estimated End Date
28/10/2022

What we are doing

Works update
We wrote to in March and April 2022 regarding works relating to ongoing work in the Network Rail land at the northern end of our site next to the rail tracks. The next phase of works will include works to the retaining wall that borders the north end of our site and the garden area of Carlton House – more information about these works is included on page 2.

Where possible, works will continue during our core working hours of 8am to 6pm Monday to Friday and 8am to 1pm on Saturdays. However, some aspects of the works will require extended working hours – please find more information about this below.

Network Rail enhancement works extended hours
Works are continuing near the Network Rail tracks to prepare for the installation of a new access ramp and site access point via Albert Road. These works are due to be completed by August 2022. As these works are near the rail tracks, to carry out some activities safely, we will be working overnight, while the train line is not in use, which has been agreed with Brent Council and Network Rail.
Overnight works will take place from 8pm on 11 June to 8am on 12 June and 9pm on 18 June to 8am on 19 June 2022, in agreement with Brent Council and Network Rail. We do not anticipate these works to be noisy, but you may hear additional noise from vehicle movements.

Retaining wall works
We will be carrying out works to remove the existing concrete blocks and fencing between Carlton House, our site and Network Rail land. We will replace this with a new retaining wall. These works will ensure that wall is structurally safe as we continue our works on site.

Works will be carried out Monday to Fridays between 8am to 6pm and Saturdays 8am to 1pm (if required) and will be split into two phases with a site set up within the garden area of Carlton House.
Site set up – from 6 July 2022, will include setting up a safety exclusion zone around the works area with fencing.
Phase one – from 6 July to 6 September 2022, will include the removal of the existing retaining wall which will involve excavations and lifting operations. We will then lower new wall segments into place and secure them with new concrete.

Phase two – from 7 September to 28 October, will include the removal of the existing retaining wall which will involve excavations and lifting operations. We will then lower new wall segments into place and secure them with new concrete.

What to expect during our works
During the works outlined in this update and other works on site you may notice the following within the site and proximity:
• Heavy good vehicles – entering and exiting site
• Excavators / excavating activities
• Cranes / lifting operations
• Lighting towers
• Concreting equipment
• Installation of new walls
• Where possible during enhancement works, restrict vehicle movements during night shifts

Reducing disruption to you
We will continue to monitor noise, light, dust and vibration in line with the HS2 Code of Construction Practice. Other measures in place to reduce disruption to our neighbours include:
• Additional attending monitoring (operatives monitoring noise and vibrations using hand held equipment)
• Operations to wash vehicle wheels as they depart site
• Dust suppression sprays on works and site roads including water bowsers during hot and dry weather
• Use of noise reducing blankets where possible
• Covering of materials, deliveries or loads entering and leaving site
• Monitoring of working methods to ensure minimal disruption is caused
• Use of electric crane
• Advise operatives to be mindful our neighbours during works especially during night shifts

Speak with your engagement team
You can contact your local engagement team via the HS2 Helpdesk, all day, every day of the year.
We will also be available to speak with you at monthly virtual drop-in sessions.
Virtual drop-in sessions until July 2022 are on the following dates:
• Wednesday 15 June, 3pm to 6pm
• Wednesday 20 July, 3pm to 6pm
To register for the next drop-in please visit www.hs2.org.uk/events/. If you are not able to attend a virtual drop-in please contact the Helpdesk so we can arrange another time to speak with you

Dates and times mentioned in this notification may change, we will keep the community updated via post, online and face to face meetings and online at hs2.org.uk.