Update: Road resurfacing on Westgate, Hanger Lane
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-2-8/02/24_02
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Westgate
- Contractor
- SCS JV
- Type of works
- Road resurfacing
- Estimated Start Date
- 12/12/2024
- Estimated End Date
- 13/12/2024
What we are doing
On the 12 and 13 December 2024, between 8am and 6pm, we will be relaying a small area of road surface at the entrance of Chelsea House following the recent reconstruction of the wall in October 2024.
Following this work we will be re-painting yellow lines. We will be removing the old tarmac using a hand breaker and a machine to peel off the top layer.
Local traffic management barriers will be in place around the works. We will maintain access to Manhattans Business Park and Chelsea House at all times