Update: Sewer works on Mandeville Road

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-26/09/2023_03

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Mandeville Road
Worksite Name
Mandeville Road
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
26/02/2024
Estimated End Date
19/02/2024

What we are doing

What we are doing
We wrote to you in November 2023, to inform you about sewer works on Mandeville Road, which were due to be completed at the end of December 2023. The sewer works are now complete.

Due to some additional design requirements, we now need to reinstate the manhole in the disused underpass opposite to Northolt Station.

These works will take place from 26 February to 19 April 2024 between 8am and 6pm.

How these works might affect you
From 26 February to 2 March and on 20 March we will need to close the first three parking bays on Badminton Close in order to accommodate a tanker or operational vehicles. On these dates, the tanker will continually pump water through the sewer 24 hours a day.

This lorry will be used to control the flow in the sewer should this be needed during the night.