UPDATE: Surveys on Old Oak Common Lane & continuation of TBM work on Victoria Road/Atlas Road roundabout junction
Work item: HS2-EW-BBVS-Ph1-OOC-St-S4-Gr-Set-49-08/11/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Old Oak Common lane
- Contractor
- BBVS JV, CS JV
- Type of works
- Ground investigations, Traffic management
- Estimated Start Date
- 23/08/2021
- Estimated End Date
- 24/09/2021
What we are doing
We previously moved away from the Victoria Road/Atlas Road roundabout to provide a period of relief to the area and are now returning to complete laying the power supply for the Tunnel Boring Machine (TBM) from 23 August to mid-September.
Along with those works, further ground investigation surveys will take place on Old Oak Common Lane from 13 to 24 September.