Update: Surveys on Parkway
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-Works-1-28/08/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Camden, Euston Approaches
- Worksite Name
- Euston Approaches
- Type of works
- Trial Holes
- Estimated Start Date
- 05/08/2024
- Estimated End Date
- 04/09/2024
What we are doing
Trial hole surveys on Parkway
We are progressing well with our work to survey the Cadent Gas main at the corner of Delancey Street and Parkway. More information on these works can be found here.
We previously informed you we would dig two trial holes. We now need to complete one extra trial hole in the footpath on Delancey Street. We anticipate this will take an extra three days and we will complete the work on 4 September.
There may be some periods of increased noise as we break out concrete. We apologise for any disruption this may cause.