Update: Surveys on Parkway

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-Works-1-28/08/2024

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Camden, Euston Approaches
Worksite Name
Euston Approaches
Type of works
Trial Holes
Estimated Start Date
05/08/2024
Estimated End Date
04/09/2024

What we are doing

Trial hole surveys on Parkway

We are progressing well with our work to survey the Cadent Gas main at the corner of Delancey Street and Parkway. More information on these works can be found here.

We previously informed you we would dig two trial holes. We now need to complete one extra trial hole in the footpath on Delancey Street. We anticipate this will take an extra three days and we will complete the work on 4 September.

There may be some periods of increased noise as we break out concrete. We apologise for any disruption this may cause.