Update: surveys planned on Greenford Road

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-5-19/05/2021-02

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Greenford
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
19/05/2021
Estimated End Date
24/05/2021

What we are doing

We wrote to you recently about drainage surveys on Greenford Road during the day between 19 and 25 May 2021.

Drainage surveys rescheduled to take place overnight
These works are still scheduled to take place between 19 and 24 May, however they will now take place overnight between 8pm and 5am.

On three consecutive nights between 19 and 22 May, temporary lane closures will be in place on Greenford Road and near the junctions of Uneeda Drive and Bennetts Avenue. Parking bay suspensions will be in place on Greenford Road.

Overnight between 24 and 25 May, temporary lane closures will be in place on the junction of Greenford Road and Rockware Avenue. You can view the location of these works and further information from our previous notification here.

Your utility services will not be affected during the surveys and you will still be able to travel through this area. The dates and locations for the surveys could change and we may need to carry out further surveys in your area. To sign up for updates, please visit www.hs2inkilburn-northolt.co.uk.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]