Update: BBVS Section of the conveyor starts operating

Work item: HS2-MW-BBVS-Ph1-OOC-St-S4-prog-works-49-25/07/2022

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Location
Old Oak Common lane
Worksite Name
Old Oak Common
Contractor
BBVS JV
Type of works
Installation Works
Estimated Start Date
19/09/2022
Estimated End Date
31/10/2022

What we are doing

Conveyor update

Works are continuing for the conveyor system between our sites in the Old Oak and North Acton area to allow for the movement of excavated material between sites. The conveyor system will help reduce the construction traffic on the local roads while we build HS2.

The conveyor structure is being jointly built by HS2’s contactors in the area, SCSJV and BBVS.

BBVS have tested and dry commissioned their section of the conveyor within the Old Oak Common Station site up to the bridge crossing over Old Oak Common Lane. The remaining BBVS section of the conveyor is being tested and commissioned during the week commencing 19 September 2022.

The BBVS conveyor is planned to be fully operational from 26 September 2022 and will run between 8am and 6pm, Monday to Friday and maintenance will take place on Saturday’s between 8am and 1pm.

SCSJV will start testing and commissioning for the SCSJV section of the conveyor the week of 19 September 2022 until late October 2022, when the conveyor will be fully operational. SCSJV will start testing and commissioning at our Atlas Road site (location 2 on the map) before moving to our Willesden Euroterminal site (location 1 on the map) and finally our sites on Victoria Road (location 3 & 4 on the map).

These works are not expected to be noisy, however there may be an audible humming noise when the conveyor runs and some other mechanical noises whilst testing is carried out. Noise from the conveyor safety start-up alarm may also be audible for short periods. We will ensure that noise is kept within permitted levels and use best practicable means, to minimise any impact on our site neighbours.
The dates outlined in this notification may change. We will provide updates at HS2.org.uk.