Update: UKPN works on Victoria Road, North Acton

Work item: HS2-EW-SCS-Ph1-Ar-So-S2 -UT-1-31/07/2024

Work Item Summary

Project Phase
Phase 1
Region
London, Old Oak and North Acton
Location
Victoria Road
Worksite Name
Old Oak Common
Contractor
UK Power Networks
Type of works
Utility works / surveys
Estimated Start Date
09/05/2024
Estimated End Date
20/09/2024

What we are doing

Works to install a new cable diversion below Victoria Road were due to be completed on 17 August. The end date for these works has now been extended to 20 September.

These works are being carried out by UK Power Networks (UKPN) on behalf of HS2. Working hours are from 8am to 10pm, Monday to Friday and 8am to 6pm on weekends.

The delay is due there being complex and extensive underground utilities networks and the need to co-ordinate the works with different organisations.