Update: Upcoming works on Adelaide Road
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-3-16/08/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Adelaide Road
- Worksite Name
- Adelaide Road
- Contractor
- SCS JV
- Estimated Start Date
- 16/08/2021
- Estimated End Date
- 31/08/2021
What we are doing
Further works on the Adelaide Road site boundary
We wrote to you in July about ongoing works to set up our Adelaide
Road site. As part of our works to install the site boundary and gates,
traffic marshals using stop and go boards will continue to be used on
Adelaide Road.
We will use stop and go boards on Adelaide Road for one hour per day
until the end of August 2021. Vehicles travelling on Adelaide Road may
be asked to wait for a short period.
These works will take place during our core hours which are 8am to
6pm, Monday to Friday, and 8am to 1pm Saturdays if required. You can view our previous notifications about ongoing works at the Adelaide Road site at hs2.org.uk/where/route-map/
The dates mentioned in this notification may change and we will provide
updates at HS2incamden.co.uk.
Virtual one to ones 22 September 2021
On Wednesday 22 September 2021 between 3pm to 6pm, we will be
hosting virtual one to ones. You can book a 20-minute session to speak
with our Community Engagement team about works at the Adelaide
Road site. The sessions will take place on Microsoft Teams. Registration will open
on 1 September; you can sign up by visiting hs2.org.uk/events.
On Wednesday 22 September 2021 between 3pm to 6pm, we will be
hosting virtual one to ones. You can book a 20-minute session to speak
with our Community Engagement team about works at the Adelaide
Road site.
The sessions will take place on Microsoft Teams. Registration will open
on 1 September; you can sign up by visiting hs2.org.uk/events.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]