Update: Utilities works on Brunswick Road and Lynwood Road
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-20/11/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing, London, Old Oak and North Acton
- Location
- Brunswick Road, Lynwood Road
- Contractor
- SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 15/04/2024
- Estimated End Date
- 06/12/2024
What we are doing
We recently notified you that Lynwood Road would reopen on 29 November, and that Brunswick Road would reopen 4 December.
The work on Lynwood Road is now complete, and the road reopened on 29 November.
The re encapsulation of the gas valve on Brunswick Road has now been completed, but this work took a day longer than expected. Brunswick Road should now reopen on 5 December. The welfare units on Brentham Way will be removed on 6 December.