Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-11/07/2024

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
West Gate
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
15/07/2024
Estimated End Date
18/07/2024

What we are doing

From 15 to 18 July 2024, we will be decommissioning the old gas main in West Gate as part of our works. As part of our emergency planning, we need to ensure we have access to the contingency valves, which are below ground in Hanger Lane and Cleveley Crescent.