Update: utility surveys at Hanger Lane roundabout

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-27/09/2022

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Ealing
Worksite Name
Westgate
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
03/10/2022
Estimated End Date
28/10/2022

What we are doing

Works planned on Hanger Lane Roundabout
We will be carrying out a series of overnight ground investigations on the Hanger Lane Roundabout between 3 to 28 October 2022. The ground investigations will take place between 10pm to 6am Monday to Saturday.

The ground investigations will consist of digging a temporary trench to confirm the location of utilities under the surface of the road and footpath. The investigations will help us to understand and aid the design of the new railway and the best ways to protect or divert any utilities during construction. We will be working as efficiently as possible whilst keeping our work areas safe and tidy.

How this might affect you
To ensure the safety of the public and our staff, temporary changes will be in place on the Hanger Lane Roundabout.
We will have bus lane and lane closures in place overnight. The footpath closures will be in place overnight and during the day, pedestrians will be able to use the subway during these works. You can view the different traffic management phases on the following pages.
Your utility services will not be affected during these works.

The dates in this notification may change. We will provide further updates here .