Work item: HS2-EW-SCS-Ph1-Ar-So-S1-UT-2-08/09/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- South Hampstead
- Worksite Name
- Adelaide Road
- Contractor
- SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 26/09/2022
- Estimated End Date
- 11/11/2022
What we are doing
Works planned on Alexandra Road
From 26 September to 11 November, we will be carrying out a series of ground investigations on Alexandra Road.
The ground investigations will consist of digging a temporary trench to confirm the location of utilities under the surface of the road. The investigations will help us to understand and aid the design of the new
railway and the best ways to protect or divert any utilities during construction.
The ground investigations will take place between 8am to 6pm Monday to Friday and 8am to 1pm Saturdays, if required. We will use noise reducing barriers where possible to help minimise any noise disruption to the local community, working as efficiently as possible whilst keeping our work areas safe and tidy.
How this might affect you
To ensure the safety of the public and our staff, temporary changes will be in place on Alexandra Road (shown on the following page). Road closures and footway closures will be in place on Alexandra Road. A clearly signed road closure and pedestrian diversion route will be in place. You can view the different locations of each traffic management on page two.
Your utility services will not be affected during these works.
Speak with our local engagement team
Our local engagement team is happy to arrange a time to speak with you via phone if you have any questions about the surveys. Please contact the HS2 Helpdesk via the contact details below to arrange this.
Dates mentioned in this notification may change, we will provide updates at hs2.org.uk/in-your-area/map
Map showing the temporary changes on Alexandra Road
Between 26 September to 11 November, road closures and a footway closure will be in place on Alexandra Road. The traffic management will be in phases and a clearly sign diversion route will be in
place for vehicles and pedestrians.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]