Update: Utility works on Adelaide Road
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-UT-1-14/02/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden, London
- Location
- Adelaide Road
- Worksite Name
- Adelaide Road
- Contractor
- SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 27/02/2023
- Estimated End Date
- 04/03/2023
What we are doing
The current lane closure on Adelaide Road, in front of the site boundary,
opposite Beaumont Walk, will be in place until 25 February 2023.
From 27 February until 4 March 2023, the lane closure will move to the
western end of the site, opposite 68–74 Adelaide Road, to allow the site
hoarding installation to be completed.
A manhole survey will be carried out on 20 February, on the footpath
between the HS2 site and Modern Motors. The footpath will be closed
while the survey is being carried out.