Update: Utility works on Eastcote Lane, Northolt

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-23/09/2022_03

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Eastcote Lane
Worksite Name
Mandeville Road
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
04/12/2023
Estimated End Date
08/02/2024

What we are doing

What we are doing
We wrote to you in July to let you know about utility protection works on Eastcote Lane between 3 July and 2 December 2023.

We’ll need to extend the end date of these works due to the discovery of a water pipe obstructing the gas pipe we are working on. We will start the next phase on 4 December and continue until 8 February 2024. These works have been scheduled for Monday to Sunday 8am to 6pm. No noisy works will be undertaken after 1pm on Saturdays and all day on Sundays.

Works on site will pause between 22 December 2023 and 2 January 2024. However, the site and hoarding will remain in place during the pause of works over the Christmas break.

During the next phase of these works, access to the church, sports centre and properties next to the church will be via Eastcote Lane North.

Bus routes using Eastcote Lane bridge will continue to be diverted via Mandeville Road.

We would like to apologise for any disruption or inconvenience these works may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way.

We will ensure that disruption is kept to a minimum.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]