Update: Utility works on Station Approach and Long Drive – Showing location for Long Drive

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-23/09/2022_02

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Location
South Ruislip
Worksite Name
South Ruislip
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
27/10/2022
Estimated End Date
14/11/2022

What we are doing

What we are doing
We wrote to you recently to let you know about our plans to carry out the main sewer protection works on Station Approach and Long Drive. These works have been rescheduled and will now take place from 27 October to 14 November 2022. These works are to reline the foul and surface sewer network and will happen overnight from 8pm to 5am, Thursday to Sunday to minimise disruption.

On three occasions we will start work from 7pm to 7am on the following dates. Friday 28 October and Wednesday 4 and 11 November 2022. This is to allow adequate curing time to complete the sewer lining works. Please note that these activities are weather dependant and may need to
be rescheduled.

We will set up a site compound at the junction of Station Approach with Great Central Avenue on Thursday 27 October from 8am to 6pm. Due to the location of our site welfare, we will close the road at the junction of Great Central Avenue with Station Approach, for the duration of the works.

There will be a clearly signed diversion route via Bourne Avenue and Primrose Gardens to enable access to Great Central Avenue.

How these works might affect you
We will be using a tanker to discharge water, as well as high pressure jet washers and we anticipate that this will create some noise. However, we will be using noise reducing barriers to minimise disruption and will limit the use of the jet washer as you as much as possible. Every effort will be made to carry out the noisiest work early in the shift.

How these works might affect you… continued
Temporary traffic lights with a single lane closure required in multiple phases. The traffic management configuration will be altered and removed each night. Traffic will be able to flow in both directions at all times.

We would like to apologise in advance for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way.

We will ensure that disruption is kept to a minimum.