Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-28/11/2023-02

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing, Old Oak and North Acton
Location
North Acton, Victoria Road
Worksite Name
North Acton, Victoria Road
Contractor
BBVS JV, SCS JV
Type of works
Utility works / surveys
Estimated Start Date
09/05/2024
Estimated End Date
17/08/2024

What we are doing

We wrote to you in December 2023 about utility works to install a new cable diversion under Victoria Road from January to June 2024. These works are being carried out by UKPN on behalf of HS2.

During the works, we have found some of the existing utility services in poor condition. We have been working with UKPN to carry out testing and additional works within our existing works areas, to help improve the conditions of the current infrastructure.

The end date for these works has been extended to 17 August, with working hours from 8am to 10pm, Monday to Friday and 8am to 6pm on weekends.