Update: Utility Works on Victoria Road, North Acton
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-28/11/2023-02
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing, Old Oak and North Acton
- Location
- North Acton, Victoria Road
- Worksite Name
- North Acton, Victoria Road
- Contractor
- BBVS JV, SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 09/05/2024
- Estimated End Date
- 17/08/2024
What we are doing
We wrote to you in December 2023 about utility works to install a new cable diversion under Victoria Road from January to June 2024. These works are being carried out by UKPN on behalf of HS2.
During the works, we have found some of the existing utility services in poor condition. We have been working with UKPN to carry out testing and additional works within our existing works areas, to help improve the conditions of the current infrastructure.
The end date for these works has been extended to 17 August, with working hours from 8am to 10pm, Monday to Friday and 8am to 6pm on weekends.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]