Update: Works on Hampstead Road and Harrington Street
Work item: HS2-MW-SCS-Ph1-Ca-S1-Site-27-28/09/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden, London
- Location
- Camden, Harrington Street
- Contractor
- SCS JV
- Type of works
- Enabling works, Traffic management
- Estimated Start Date
- 01/10/2021
- Estimated End Date
- 14/10/2021
What we are doing
Update: Works on Hampstead Road and Harrington Street
We are currently moving the utilities beneath Hampstead Road from the footway to the carriageway, to clear our working area for piling. We expect to continue these works until spring 2022.
British Telecom will divert their services from mid-October 2021 to February 2022, which will require lane and footway closures on Hampstead Road. We are waiting to confirm with Transport for London whether we will suspend any bus stops during these works.
We try to use our Hampstead Road gate as often as possible to reduce construction traffic on residential streets. There are periods where we are unable to use this gate due to works being carried out in this location. To maintain site access from Hampstead Road during upcoming utility works, we are creating a second gate south of the current gate. We will require additional traffic management on Hampstead Road during November while we install the access.
We may need to work during weekends and extended hours to install this access as quickly as possible and reduce our impact on local traffic. We will update you once we have confirmed details.
Once we have extended Granby Terrace bridge, we will divert the utilities on Hampstead Road across Granby Terrace, to clear Hampstead Road for bridge extension works. This will be a temporary measure. Once we have extended Hampstead Road bridge, we will reinstate the utilities.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]