Update: Works on Park Village East
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-1-06/04/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Camden
- Worksite Name
- Park Village East
- Contractor
- SCS JV
- Type of works
- Lorry lay-by set-up, Worksite / compound set-up
- Estimated Start Date
- 11/04/2023
- Estimated End Date
- 11/05/2023
What we are doing
Park Village East closure for lay-by works postponed
We previously informed you we would close Park Village East from 10 April to the end of May to
- extend the hoarding around the existing lorry lay-by at the northern end of Park Village East
- create an access within the hoarding to a new welfare building
- install a second hoarded lay-by at the southern end of Park Village East.
The lay-by extension, new welfare building and second lorry lay-by will be put on hold so the road closure is not required now. The existing lorry lay-by will revert to its original layout and remain operational. We are continuing the design of the welfare building and will update you when we have more information.
Mornington Street bridge closure remains in place
Mornington Street bridge will remain closed to vehicles whilst monitoring and works beneath the bridge continue. It remains open to pedestrians and cyclists, with the Park Village East one-way system in place.
Maintenance to planter on Park Village East postponed
We planned to close the footpath and suspend three parking bays at the northern end of Park Village East to trim the overhanging trees and bushes in the planter. We have delayed these maintenance works until after Easter.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]