UPDATED Notice of Traffic Management, Gawcott Road, Calvert

Work item: HS2-EKFB-25-1499

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Gawcott Road
Worksite Name
Calvert
Contractor
EKFB JV
Type of works
Traffic management
Estimated Start Date
23/10/2025
Estimated End Date
19/11/2025

What we are doing

Location
Gawcott Road, Calvert at the spur road servicing the EKFB compound.

Duration
Traffic management will be in place from Thursday 23 October until Wednesday 19 November 2025.

What we are doing
Connecting the Anglian Water asset to the existing pipe, including excavating, pipe and valve installation, backfilling and compaction.

What to expect
Three-way temporary traffic lights. Varied activities with both quiet and busy times.

HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]