Updated notice of works at Gate Street – Birmingham
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-UT-14-05/03/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Birmingham, West Midlands
- Location
- Saltley
- Worksite Name
- B8 1JG
- Contractor
- BBV JV
- Type of works
- Road closure
- Estimated Start Date
- 04/09/2023
- Estimated End Date
- 22/12/2023
What we are doing
We recently wrote to you regarding a temporary one-day closure of Gate Street on Friday 25 August to carry out utility surveys within the road and footpath.
After these surveys are complete, we will then require a series of closures along Gate Street from Monday 4 September until winter 2023. During this time, we will carry out utility diversion works.
Access to businesses will be maintained under marshal control during these works.