Upgrading utilities: Installing temporary cable diversion

Work item: Reference number: HS2-MW-BBVS-Ph1-OOC-St-S4-***-04-23/09/2024

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Location
Old Oak Common lane, Wells House Road
Worksite Name
Old Oak Common
Type of works
Cable works, Construction
Estimated Start Date
12/11/2024
Estimated End Date
28/03/2025

What we are doing

As we continue with the works at Old Oak Common Station, we need to renew the old and outdated 132kV UKPN electrical cables behind properties 53 to 135 Wells House Road. This requires a temporary diversion (more information on page 3) which we’ll be starting in November. We will then upgrade existing cables to ensure the modernisation of the network ahead of the opening of the station.

They need to do this work as part of our wider utility improvement plan to modernise the current outdated network as part of a risk mitigation strategy to allow for further construction works.

These works will take place during core working hours, Monday to Friday 08:00 to 18:00, Saturday and Sunday 08:00 to 13:00.

Please see the link below for further information.