Utilities works on Bideford Avenue, February to March 2024

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-30/01/2024

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing, Greenford
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
26/02/2024
Estimated End Date
07/03/2024

What we are doing

From 26 February to 7 March 2024, we will be carrying out utility works to strengthen the existing sewer pipe underneath Bideford Avenue. During these works we will be switching between different traffic management phases. Depending on the phase, these works will take place during the day and overnight.

During the day, working hours will be 8am to 6pm, Monday to Friday, and 8am to 1pm Saturdays (if required). Overnight working hours will be from 8pm to 8am Friday to Sunday.

We will use noise reducing barriers where possible to help minimise any noise disruption to the local community, working as efficiently as possible whilst keeping our work areas safe and tidy.

Download information relating to these works